IRAK - Süleymaniye Uluslararası Havaalanı ve Terminal Binası Anahtar Teslim İnşaatı

SULAIMANIYE ULUSLARARASI HAVA ALANI PROJES ACIKLAMASI: 

A- INFRASTRUCTURE WORKS:

- CONSTRUCTION OF A NEW RUNWAY OF 3,500m LONG and 45m WIDE
TOGETHER WITH 7.5m CONCRETE PAVED SHOULDERS+ 45m WIDTH:

A1- COMPACTED EARTH SHOULDERS ON EACH SIDES + 60m x 60m - CONCRETE PAVED CLEAR ZONES ON EACH END OF THE RUNWAY WITH ALL INFRASTRUCTURE FACILITIES.

- CONSTRUCTION OF TWO CONNECTION TAXI TRACKS AND TWO HIGH SPEEDTAXI TRACKS ACCORDING TO THE DRAWINGS AND INTERNATIONAL STANDARDS MENTIONED IN TECHNICAL DOCUMENTATIONS WITH ALL INFRASTRUCTURE WORKS.

- CONSTRUCTION OF PARALLEL TAXIWAY of 3,500m LONG AND 35cm BASE AND 40cm QUALITY PAVEMENT CONCRETING OF EXISTING 30m WIDE RUNWAY+ 3m CONCRETED PAVED SHOULDERS+ 12m WIDTH COMPACTED EARTH SHOULDERS ON EACH SIDE WITH ALL INFRASTRUCTURE FACILITIES.

- CONSTRUCTION OF A NEW APRON WITH 40cm QUALITY PAVEMENT
CONCRETING ACCORDING TO THE DRAWINGS.

B- SUPERSTRUCTURE WORKS:
(With all furniture, computer and telephone  systems and all other necessary equipment (kitchen, etc) included, Turn-Key basis)

- CONSTRUCTION OF THE INTERNATIONAL TERMINAL BUILDING OF 1,600,000 PASSENGERSNEAR CAPACITY WITH ALL FACILITIES

- CONSTRUCTION OF CONTROL TOWER OF 31 METERS HIGHT

- AIRPORT MAIN ENTRANCE BUILDING

- TECHNICAL AND ADMINISTRATION BUILDING

- ACCIDENT AND FIRE EXTINGUISH BUILDING

- SECURITY BUILDING

- SHED FOR APRON VEHICLES

- GARAGE FOR HEAVY VEHICLES

- POWER SUPPLY BUILDING

- H1 AND H2 REGULATOR BUILDINGS

- PERIPHERIAL SECURITY TOWERS

- CATERING SYSTEM BUILDING

- CARGO FACILITY BUILDING

- METEOROLOGY BUILDING

C- ELECTRICAL WORKS AND ELECTRONICAL SYSTEMS:

RLS - MAIN RUNWAY, TAXIWAY. TAXI TRACKS AND APRON LIGHTING AND SIGNING SYSTEMS ACCORDING TO "ICAO" STANDARDS.

RLS -APPROACH LIGHTING SYSTEM ON EACH TWO ENDS OF RUNWAY ACCORDING TO "ICAO" STANDARDS, "A" TYPE (CAT I) 

RLS - MAIN RUNWAY, TAXIWAY, TAXI TRACKS AND APRON LIGHTING AND SIGNING SYSTEMS ACCORDING TO "ICAO" STANDARDS. (ALL INFRASTRUCTURE WORKS ACCORDING CAT II)

- RUNWAY "PAPI"

- APRON ILLUMINATION (4 POLES, 25 METERS, WITH LIFT) 

- LIGHTING OF SECURITY ROAD 19 km

- 2*5MVA MAIN (33/11kV) POWER DISTRIBUTION STATION (800kVA+ 2*500kVA TRANSFORMER AND 800kVA+2*500kVA   GENERATOR S)

- SUBSTATION TRANSFORMERS (H1 AND H2 REGULATOR BUILDINGS) 2 * 250 KVA AND 2*225 KVA GENERATORS.

 - CONTROL CABLES BETWEEN H1, H2 AND CONTROL TOWER

- CONTROL TOWER COMMUNICATION SYSTEM

- VHF/UHF AIR-TERRAIN STABILE WIRELESS SYSTEM

- VHF/UHF AIR-TERRAIN EMERGENCY WIRELESS SYSTEM

- VOICE COMMUNICATION CONTROL SYSTEM (VCS)

- ATIS -AUTOMATED TERMINAL INFORMATION SYSTEM

- AFTN - AERONAUTICAL FIXED TELECOMMUNICATION NETWORK

- VOICE REGISTRATION SYSTEM

- AIR TRAFFIC HELPING SYSTEM

- DVOR/DME SYSTEM - DISTANCE MEASUREMENT EQUIPMENT / DOPPLER OMNI

- DIRECTIONAL RADIO RANGE

- ILS - INSTRUMENT LANDING SYSTEM (Localizer, Glide Path, Marker)

- AIRPORT METEOROLOGICAL SYSTEM (AWOS)

- PERIPHERIAL AND AIR/TERRAIN SEPARATOR SECURITY FENCE ; 19km

- PERIPHERAL SECURITY ROAD ; 14 km + INNER ROADS ; 3km + ACCESS ROAD; 1,5km

- WATER TANK (400 TONS)

- SEWAGE WATER TREATMENT PLANT (400 m3) AND CONNECTION OF ALL FACILITIES

- FUEL STORAGE TANKS (2 * 250 TONS)

- OPEN PARKING AREAS OF TERMINAL BUILDING AND OTHER BUILDINGS